Example situation
The finance team wants to understand why invoices wait even after improving parts of the process.
Typical model inputs
- Flow unit
- invoices
- Demand
- 500 invoices per week
Capacity signals
Data validation
540 per weekEnough capacity, but quality issues create repeat work.
Manager approval
430 per weekCurrent limiting capacity.
Payment release
700 per weekNot limiting at current volume.
Improvement test
Improving approval availability changes system output; improving payment release alone leaves the constraint unchanged.